Timeline

Sept 24, 2009 - Proposal Finished and Ready for Internal Review
Oct 1, 2009 - Transmit Proposal to NASA
Oct, 2009 - Rocketry Basics Workshop with new IASA members. Begin formal design work. Identify best vendors for materials. Compile acquisitions list by vendor for action upon notification of award.
Oct 22 2009 - Awards Granted, Schools Notified
Oct-Nov, 2009 - Acquire supplies from vendors. Begin work on scale model of proposed vehicle design.
Nov 5, 2009 - Web Presence Re-established with specific SLI section on site
Nov 24, 2009 - Preliminary Design Review (PDR) Finished and Ready for Internal Review
Dec 4 2009 - Transmit PDR to NASA
Dec 7, 2009 - Scale Model of Proposed Vehicle Ready for Test Flight
Dec 10 2009 - NASA teleconference during 5th period
Jan 2010 - Test all systems
Jan 2010 - Workshop with Latino Achievers' Club
Jan 6, 2010 - Safety Briefing Refresher for all project personnel
Jan 13, 2010 - Critical Design Review (CDR) Finished and Ready for Internal Review
Jan 20, 2010 - Transmit CDR to NASA, Motor Selection due
Feb 3, 2010 - CDR Videoconference with NASA Reviewers
Feb 26, 2010 - All subsystems ready for integration
Mar 6, 2010 - Full scale vehicle flight readiness launch
Mar 10, 2010 - Flight Readiness Review (FRR) Finished and Ready for Internal Review
Mar 17, 2010 - Transmit FRR to NASA
Mar 27, 2010 - Second Test Flight
Mar 31, 2010 - FRR Videoconference with NASA Reviewers
April 14-19, 2010 - Travel to Huntsville for SLI events
May 14, 2010 - Post-Launch Assessment Review (PLAR) Finished and Ready for Internal Review
May 21 2010 - Transmit PLAR to NASA